Hi Steve (I happen to know your real name…),
Microsoft has acknowledged this to be a current issue (dare I say ‘bug’?). Adrian Jenkins from Microsoft wrote in our MVP-discussion group “There are actually two parts to this fix one that is already on the servers and other in Project Professional”. Gary Chefetz, another MVP, reports that the first build of Project Server (Project Online) to fix this is: 16.0.6001.1061 . Look for builds that have that or a later release build number.
Hope this helps!
Eric Uyttewaal, PMP, MVP in Project