Reply To: Manually spread material costs over project duration.

Home Forums Discussion Manually spread material costs over project duration. Reply To: Manually spread material costs over project duration.

#387799
Larry Christofaro
Participant

Edrisa, try going into a usage view such as Task Usage, define the timescale as monthly, and enter the material as desired. You should be able to set it up however you want. Hope that helps…