Reply To: Project Server View Setting

Home Forums Discussion Project Server View Setting Reply To: Project Server View Setting

#387834

Yes. There are 5 hours columns for budget work, actual work, remaining work, projected work and work variance. All 5 of those hours columns have to show “0” for that row to not show up.