Robert, a general suggestion is to put those tasks under a summary task and mark that on the master project. Another thought is to build what I would call a program project. This project would link the key tasks from each of the sub projects to a higher level project. Then you could create an external link to all 10 Mechanical Assembly tasks and then schedule those under a summary task in your program project. Hope that helps…