Loading...
Quick Links

Reply To: MS Project 2013 – expert help and advise required

Home Forums Discussion MS Project 2013 – expert help and advise required Reply To: MS Project 2013 – expert help and advise required

#389507
Larry ChristofaroLarry Christofaro
Participant

Ramil, try using Fixed Work and your task type. That will change the units when duration is changed. Hope this helps…