Reply To: how to add weekends as a workday to my gannt chart ?

Home Forums Discussion how to add weekends as a workday to my gannt chart ? Reply To: how to add weekends as a workday to my gannt chart ?

#392535
Rick Yoder
Guest

When I build a 6 work day calendar to include Saturdays in my work week and I set the calendar for a task in the advance tab, to 6 day work Calendar…my task using the 6 day calendar start having 1/2 days or partial days show up on the Guant Chart.
How do I correct this?
Note: I use MS Project for scheduling construction projects…we don’t use the Resource Loading or Hours…we strictly use whole days.