Larry Christofaro
Participant

Pawel, assuming you are using Project 2013 or higher you should be able to get both reports from the Reports function. If you are using fixed cost task field you can get them both using a task view. If you are using materials resources then it might require a bit of tweaking. Reporting on tasks and resources can be a challenge. One option is to (1) make sure that the material resources are assigned separate from work resources, and (2) flag the material tasks using a task custom field. After that I’m thinking you can use filters to filter out tasks for report one and time for report two. Hope that helps…