Home › Forums › Discussion › Limit the fields showing when you click Project Information in Project Pro › Reply To: Limit the fields showing when you click Project Information in Project Pro
John, you are correct that it does not include multi-line fields. Start and Finish dates are controlled by MS Project so the Start date is typically the date you key in on top, and the Finish date is the project finish. The order unfortunately is alphabetic grouped first by required fields and then by non-required fields, and no you cannot change this order. I typically create the organized fields within PWA and try to move PMs to use that instead (whether they use multi-line fields or not).