Hi everyone,
it took a bit longer to test but…Project Pro June CU does contain a fix for ONE of the ways that inserts 0 actuals in the future.
The scenario describing the fix is exactly the one we have reported to Microsoft, so that’s good news.
However, it was just one symptom that we had identified, as there are plenty more ways of creating the problem, I unfortunately have to report that neither the Project Pro CU nor the Project Server CU fix this issue.
It’s not exactly back to square one, as we definitely are progressing on this issue, but it’s a long slow and painful process… the project manager team’s confidence in the product is at a record low…
We’ll keep working on the case and if we ever find a solution to this problem, I will post back on this forum.
thanks to all that follows this thread and participate.
Jeremy