Reply To: Project 2013 not saving newly added subprojects to consolidated master project

Home Forums Discussion Project 2013 not saving newly added subprojects to consolidated master project Reply To: Project 2013 not saving newly added subprojects to consolidated master project

#399015
Jon Green
Guest

Think I’ve sorted it. I was adding the subprojects while the consolidated project was showing ‘All subtasks’. This meant the new subprojects were added as new tasks to the last open subproject rather than individual subprojects. When opened again after the save then these disappeared. Changed the consolidated view to ‘Hide Subtasks’, added the new subprojects (these now inserted correctly as individual subprojects), saved the changes, re-opened and all now OK
Thanks for your time and help on this – reallly grateful and good to solve it