Reply To: How do I manage the start/end and units for a single resource in shared tasks?

Home Forums Discussion How do I manage the start/end and units for a single resource in shared tasks? Reply To: How do I manage the start/end and units for a single resource in shared tasks?

#399109
Seth
Guest

Thank you for your response.

To answer your questions: Scott can only work the second week as that week overlaps with another project that has dates that cannot be altered, but the task on the mentioned project (and the other two workers assigned to it) must begin work on it immediately in order to come close to hitting the deadline (i.e. pushing them all back by a week would lose too much time).

I have not leveled the projects yet.

Where might I find the three part series on leveling using Microsoft Project?