Larry ChristofaroLarry Christofaro
Participant

Yea, that one’s a tough one unless you know that Scott can only work one of the two weeks. It’s kind of a catch 22. You are setting up your project so you haven’t leveled yet, but you need to know that he can only work one of the two weeks. That will need to be and adjustment to the leveled plan. Of course, then the plan changes and he becomes available here but not for another task. It’s kind of a circle, and depends on how much time you want to spend on it. The recordings are here: http://www.mpug.com/education/managing-a-resource-constrained-project/. Good luck and let me know if they help.