Reply To: Critical Path to multiple deadlines

Home Forums Discussion Critical Path to multiple deadlines Reply To: Critical Path to multiple deadlines

#400068
Larry Christofaro
Participant

Best option out of the box is to use the Task Path feature (Format, Task Path, Driving Predecessors). Unfortunately this is just a Gantt view option and does not extend to a custom field. Otherwise you might be able to use VBA (not my expertise). Hope that helps…