Loading...
Quick Links

Reply To: Task duration runs through non-working days – fixed, but don't know why?

Home Forums Discussion Task duration runs through non-working days – fixed, but don't know why? Reply To: Task duration runs through non-working days – fixed, but don't know why?

#400288
Larry ChristofaroLarry Christofaro
Participant

Tim, I’m not sure how the task started at 1700 but that could be a fluke with the actual time a predecessor ended. You can do some further analysis next time by changing your date format (File / Options / General) to a date and time format and see exactly what is driving the task. The Gantt bar is normal behavior. If the task started on Friday then the bar will span the weekend by default. Hope that helps…