Reply To: WBS Renumbering not working with MS Project 2010

Home Forums Discussion WBS Renumbering not working with MS Project 2010 Reply To: WBS Renumbering not working with MS Project 2010

#400319
David Cann
Guest

So in my project plans the renumberoption is always greyed out.
I inheritted this plan from others and the WBS codes were all over the place, (EG sequence: 1.2.3.10.3, 5.1, 1.2.3.10.2, 09-12).
There was no custom code setup this had just been corrupted along the way somehow.
To fix it I was going to follow the Outline Number workaround.
However all I actually had to do was highlight each of the WBS tasks in the plan (note I did not select the column, click the first task – hold shift – click the last task – all withing the WBS column) and then press ‘Delete’.
When I pressed ‘Delete’ the numbers there were removed and automatically replaced with the correct number format that MPP defaults to.
Hope this helps others.