Reply To: Can I allow 5 days for a task and only assign resource for 2 days

Home Forums Discussion Can I allow 5 days for a task and only assign resource for 2 days Reply To: Can I allow 5 days for a task and only assign resource for 2 days

#400736
Julie Sheets
Guest

Set the task as a Fixed Duration task. Split your screen to show the task form in the bottom pane. Select the resource’s name from the drop down under the Resources heading in the task pane. Enter 16 hours of work in the work column. Click OK.