Reply To: Generic schedule-specific start and finish dates

Home Forums Discussion Generic schedule-specific start and finish dates Reply To: Generic schedule-specific start and finish dates

#401052
Larry ChristofaroLarry Christofaro
Participant

Stergios, good question. You can change the Gantt date format using the Layout function (Format ribbon/Layout or right click on the Gantt chart. Unfortunately they all represent a date, but one indicates week/day number. If that doesn’t work you might looking into using a custom field to format the date the way you want (concatenating text with the date difference from the project start, or however you want).
Hope that helps…