Reply To: WBS Renumbering not working with MS Project 2010

Home Forums Discussion WBS Renumbering not working with MS Project 2010 Reply To: WBS Renumbering not working with MS Project 2010

#401315
Drew Pokorney
Guest

I had the same problem – my tasked copied from an Excel List. Linton Smith’s solution worked for me – THANK YOU Linton! SOLVED!

“Create WBS and change the type of numbering to letters for all levels. Create WBS and Renumber.
THEN Create WBS and change the type of numbering back to your preference. Create WBS and Renumber.

Ordering and numbering should be top to bottom and sequential.”