Bar and Amir, this can be done but does require a bit of setup (also note that it is probably one milestone at a time). Two steps to get there. First, on the Gantt, go to Format / Task Path and choose to highlight predecessors. This will show all predecessors for a particular task. Second (and this is the manual part), add the Marked column or create a custom flag field to make all tasks that are highlighted for a specific milestone. Now you can create a report filtering for that custom field. It’s a bit manual and you can only do one milestone at a time, but there is no out of box option to group or show predecessors for each milestone in a single report. Hope that helps…