Reply To: Managing resources in a matrixed organization for future projects

Home Forums Discussion Managing resources in a matrixed organization for future projects Reply To: Managing resources in a matrixed organization for future projects

#402353
Larry Christofaro
Participant

Earl, I’m not sure what a resource field will do for you as it is tied to the resource (not the project) and not time phased. I might suggest two ways of tracking both the notional (original) staffing (estimates) to current. The first obvious that comes to mind is the baseline. That is designed as the original plan. If that’s too complicated or the project isn’t in a schedule at the time, you should take a look at Resource Plans (or Resource Engagements if you are using Project Online). This is designed as a higher, project level staffing requirement for a project. Hope that helps…