Reply To: Why do some tasks update to end of current day, some to end of previous day?

Home Forums Discussion Why do some tasks update to end of current day, some to end of previous day? Reply To: Why do some tasks update to end of current day, some to end of previous day?

#402627

often time for me, the issue is in the the date/time. Try showing the time in the date field and you’ll likely see that the start time is later in the day. Once Project calculates the finish based upon your default day, it will often push the finish into the next day. Just set your start time to earlier in the day… this often corrects the issue (assumes that you’re tracking days and not hours).