George, you are off to a good start. My biggest suggestion is that you seem to want to convert the actual printers installed to a %. I would suggest that you use a Resource Usage view and enter the actual number per period in the timephased section of the view. This will update the % Complete. Time phased updates are important for EV. I don’t tend to use Physical % Complete because it is all manual compared to % Complete, but it becomes necessary when you want to consider learning experience (the first printer will take longer to install then the last printer so even though they are half way through their estimated effort/timeline, they are less then half way through the number of printers). I just haven’t had a situation where that was necessary. Good luck…