Reply To: Project defaults certain tasks to 100% when a lower percent complete is entered.

Home Forums Discussion Project defaults certain tasks to 100% when a lower percent complete is entered. Reply To: Project defaults certain tasks to 100% when a lower percent complete is entered.

#402837
Howard
Guest

I found this description of why the problem occurs. I was able to resolve the issue by setting the duration to 1 day, then changing the task type from “Fixed Duration” to “Fixed Units” then back to “Fixed Duration”. I then set the duration of the task back to the real duration.

https://social.technet.microsoft.com/Forums/projectserver/en-US/b5899421-8954-47af-b47e-d5ef74a74b48/complete-jumps-to-100?forum=projectprofessional2010general