Loading...
Quick Links

Reply To: Why do some tasks update to end of current day, some to end of previous day?

Home Forums Discussion Why do some tasks update to end of current day, some to end of previous day? Reply To: Why do some tasks update to end of current day, some to end of previous day?

#403345

This may be out in left field, but I’ve seen similar symptoms in other parts of the tool that were cause by a couple things. First, un-aligned calendars. For example, the Standard project calendar work days are 8-12 and 1-5 but some of the resource calendars are set to work days of 8-4. Additionally, I’ve seen this occur when the Calendars don’t match the default hours/day set in the Options. For example, the default Day = 8, but calendars indicate a different value such as 7.5 or 9. In this scenario, the durations were being entered as 4D meaning the D value was controlled by the default Days duration and not the resource calendar. Like I said, it’s a long shot.