Marcelo Guedes
Guest

Hello Bob,

Unfortunately, the behaviour you described is the correct from the software standpoint. Keep in mind that you also can solve this question adjusting, directly in right-side (chronological view), the assignments units’ from each month (but I particularly believe that is not an elegant solution).