Reply To: Can you have a resources units change part way through an assignment?

Home Forums Discussion Can you have a resources units change part way through an assignment? Reply To: Can you have a resources units change part way through an assignment?

#404036
Sai Prasad
Participant
  • Community Leader
  • Forum Pro

Emma, Are the tasks assigned to the same team member done in parallel or in sequence? If it is a sequence, you will not need to make changes in units as they don’t overlap. If it parallel tasks where one completes sooner (see this picture https://i.imgur.com/UFzrW4F.png) and you want the team member to work 100% once the first tasks is complete (in this picture it is 3rd and 4th day), then change the view to Task Usage and edit the hours per day assigned to the team member (see this picture https://i.imgur.com/SXXZUyo.png)