Reply To: Lag and elapsed time

Home Forums Discussion Lag and elapsed time Reply To: Lag and elapsed time

#404037
Sai Prasad
Participant
  • Community Leader
  • Forum Pro

This is definitely a BUG and not default behavior in Project 2016. This is reported to Microsoft and you should expect it to be fixed in the next update. Till that time, remove the “e” from the predecessor.