Home Forums Discussion Master schedule – Group-by Reply To: Master schedule – Group-by

#404273
Larry Christofaro
Participant

I can at least get you started. Try this to add subprojects into a single set of tasks. When you insert the project, on that insert project selection window, deselect the Link to Project checkbox. That will insert the tasks into your project as part of the project itself. Then you can do what you want with it being a single project. You will need to rebuild your temporary master project each time but hopefully better than not having a solution at all. Good luck…