Loading...
Quick Links

Reply To: Can I allow 5 days for a task and only assign resource for 2 days

Home Forums Discussion Can I allow 5 days for a task and only assign resource for 2 days Reply To: Can I allow 5 days for a task and only assign resource for 2 days

#404468
John RiopelJohn Riopel
Participant

In the task form, that you have in the split view, you can right click, select the schedule view to even set which dates you want each resource to work. Using the work view in the split view will allow you to set each resources individual work value.