Thank you for such quick reply Larry.

Now, I went through your suggestions:

1. No actual start is present on the task (NA under the column)
2. All tasks in the plan are auto scheduled (I forgot to write that in my original message)
3. Both task and work plan were recreated from scratch – even names were re-typed and not copied

The strange thing about this error is that we have both these resources across 3 other plans and only this one (with that task) is having problems. I start to think that both resources are corrupt in some way, but I am not 100% sure.

Current workaround for me is switching task type to fixed work (due to task starting April ’17, there’s no need to lock the duration at the moment).

I’ll post an update if that helped (or if i find a solution).
Thank you again