Home Forums Discussion The resource is assigned outside … & difference between work and cost values Reply To: The resource is assigned outside … & difference between work and cost values

#404773
Larry Christofaro
Participant

Tomas, very strange. That was going to be my next suggestion and forgot to add it. If switching it to fixed work fixes the problem, then try switching it back and see if the fix holds. Did you say that all tasks are fixed duration or just this one? If that doesn’t work then I would say it is a bug in the PSI.