Reply To: Flags in Summary Tasks

Home Forums Discussion Flags in Summary Tasks Reply To: Flags in Summary Tasks

#405204
Tim Jones
Guest

This might come close to what you’re looking for:

Use a custom Number field and enter the following formula: IIf(([Finish]>[Deadline]),1,0)

Select “Rollup, Maximum” for summary row calculation.

Create a red flag graphical indicator for when the custom Number field equals “1” for summary rows.

I can provide more on how to do it if you can’t get it working.