Reply To: Flag1 automatically being inserted into table

Home Forums Discussion Flag1 automatically being inserted into table Reply To: Flag1 automatically being inserted into table

#406338
Larry Christofaro
Participant

Megan, hard to tell how that happened but I assume your global table got updated somehow. I’m not sure how comfortable you are with updating the global but I’ll toss out some general steps here. There are also lots of blogs and videos that can help.
1. Launch Project with the one blank (Project1) project open, then and go to a view that contains the Flag1 field. Note the name of the table (The Gantt Chart view should connect to the Entry table).
2. Remove (hide) the Flag1 column
3. Go to File ribbon, Info, and Organizer. You should notice the Global.MPT on the left and Project1 on the right
4. Select the Tables menu, select the table in question (like the Entry table) and then select to copy it to the Global side (select to replace).
Hopefully that should work. If not then feel free to reply with what you are getting and we can work on it. Thanks…