Are you connected to Project Server? If this is happening with multiple users then that leads me to Project Server. Another option is to rename your global and let Project create a new one. Go to: C:\Users\(username)\AppData\Roaming\Microsoft\MS Project\14\1033 (the number 14 is for 2010 and may be different depending on the version you are using). Rename the Global file. There may also be one or many folders inside the Cache folder. Delete all of them as well. Then open Project again and see if that solves your problem. Hope that helps…