That depends a lot on how you are asking Project to schedule. If you are using predecessor relationships, then you need to adjust your predecessors. My guess is that you are trying to use Microsoft’s leveling. If that’s the case then you should include task priorities. (1) include the Priority field, (2) set priorities so that each site is scheduled as you want. You can probably use the same priority for an entire site, but I don’t know your project. Then (3) set the Leveling Order in Leveling Options to Priority, Standard. Hope that helps…