Larry Christofaro
Participant

Edgardo, are you asking about a progress bar in the Gantt chart? I don’t remember any version that shows a progress for summary tasks, but you can add that to the Gantt view by using the Bar Styles option. Go to the Format ribbon, Format, Bar Styles. Copy the current Progress Bar style to a new line under the existing styles, and enter the contents of the Show For…Tasks similar to the Summary Task or Manual Summary task. Hope that helps…