Reply To: How do yo convert a detailed MS Project Schedule to a High Level Gantt Chart?

Home Forums Discussion How do yo convert a detailed MS Project Schedule to a High Level Gantt Chart? Reply To: How do yo convert a detailed MS Project Schedule to a High Level Gantt Chart?

#406736

Amy;
To add on to Jigs comment, you can create a temporary master schedule by opening each schedule individually, which will result in “X” number of open windows. Then on the View ribbon, click New Window. A pop-up will appear asking which of the already open schedules to include in the new window. Select all the schedules and click OK. Now you have “X” schedules stacked on top of each other in the same window. From here you can easily create a summary Gantt view simply by displaying the first level WBS of each schedule, or more detailed WBS levels as necessary if you wish to display progress on key deliverables within each schedule.
Since this is a temporary master schedule, you’re not saving it and therefore customized views created in that temporary master aren’t saved either (unless you add them to your global), but if the view is simple enough that it only takes a minute to recreate it, this may be an option. The benefit is that you have no master schedule to worry about because you only create a temporary master when you need a reporting view.
Just a thought…