Reply To: Link between Project and Excel

Home Forums Discussion Link between Project and Excel Reply To: Link between Project and Excel

#406803
Larry Christofaro
Participant

Jigs has a good point. Question for you is what you mean by linking data between Project and Excel. If you are looking for a dynamic link between the two applications, that doesn’t exist. There is a feature that allows you to import or export to/from Project and Excel if that works. One MPUG article from Ellen Lehnert is here: https://www.mpug.com/articles/ask-expert-import-excel-data-project-tips-troubleshooting/. There are also other description online. Hope that helps…