Stergios,
I found that issue as well and this is how I resolved it
To highlight the critical path:

• Click on Format; Set the Critical Tasks flag
• Click on Format painter; Select Bar Styles;
o Add a bar called Critical Path and select Critical (tasks) from the Show For menu
o Change the color of the Critical Path (Middle setting) to red to make it visible
o Select the text tab and include the %Complete or %Work as well as resources names/initials in the text
• Click on Format; Click on Text Styles at the far left; select Item to change and critical tasks; Change the colour to red