Reply To: Update Progress from another Microsoft Project File

Home Forums Discussion Update Progress from another Microsoft Project File Reply To: Update Progress from another Microsoft Project File

#407070
Kris W
Guest

I had high hopes for the Compare Project feature, but unfortunately with the contract altering the order of the tasks, the report doesn’t cope well with the change in sequence, and that’s before it even looks at the predecessor and successor link IDs

I think I’ll have to restructure my files to match the new files before updating, so all the task IDs align.
Its the only work around I can think of at the moment