Megan, Daryl reminded me of the quick fix I couldn’t remember…thanks Daryl. Daryl has the right answer but this might be a bit quicker. Copy the entire predecessors column to another custom field, delete all predecessors, and then copy them back in. If you have a circular reference, the error message will tell you along with the task that is causing it. It might still be a bit of research to work through the circular reference, but that should make your research across multiple projects a bit easier. It’s been a while since I’ve tried this but you might want to open all projects and go through them one at a time. Good luck…