Home Forums Discussion Consistent duration units – summary tasks in months, tasks in days Reply To: Consistent duration units – summary tasks in months, tasks in days

#407847

Hey Steven, I stumbled across an old MPUG article about consistent duration formatting in Project. Apparently MS used to provide a macro to do this exact function but in their infinite wisdom, stopped providing it with 2010 and later versions. I did however find a location where a version can be downloaded. I didn’t down load it and I haven’t tried it, so please research it well to make sure it can work on your version of project.

https://social.msdn.microsoft.com/Forums/en-US/4650bc37-c47d-4720-b32b-69617f9e5d5e/free-format-duration-vba-macro-for-project-2010?forum=project2010custprog

Hope this helps.