Daryl has probably the best Microsoft answer. Using Visual Reports with Visio is a good option. You will need Visio Pro to integrate the two. Another option if you want a more complete solution is a package called WBS Schedule Pro. That allows you to start the project visually (like you describe) and then build your schedule from the results (and synch to two). It is a bit expensive but so is Visio Pro so at least worth a try. There may also be other packages if you do some searching. Good luck…