Reply To: Updating MS Project/PWA from Excel

Home Forums Discussion Updating MS Project/PWA from Excel Reply To: Updating MS Project/PWA from Excel

#408265
Larry ChristofaroLarry Christofaro
Participant

This might be a bit outside the box but maybe the best solution is to allow them to keep their schedules in Excel. Create a Project Type for them that doesn’t display the schedule tab will allow them to track projects but with no schedule. If they save their Excel task list in SharePoint you could add a field for “Excel Tasks URL” that will give others a path to the document. Hope that helps…