Just to close this out …
We decided to have the UK Projects mapped to the UK 37.5 Hours per Week calendar. So when a UK resource is assigned a 5 day task, the it is 37.5 hours of work. For tasks to be assigned to India resources, we set the duration to be in hours … 8 hours per day to match our India team’s calendar.
Thanks
John