John,

I have an 800 resource-/500 timesheet submitter-install, and we have enabled the feature to protect project actuals. You should be able to do this too, so the actuals in the project schedule can no longer be updated manually by a PM, but only through task/timesheet submittals. When I saw this as a user/PM at my last job, it was a big frustration. As a Project Admin, I no longer allow this type of corruption to the timesheet actuals.

Hope this helps,
Marty