Reply To: Resource's Unique Calendar Not Being Reflected In Task

Home Forums Discussion Resource's Unique Calendar Not Being Reflected In Task Reply To: Resource's Unique Calendar Not Being Reflected In Task

#408641

I realized the issue after reading this post

The project start date time under Project>>Project Information was after Deb’s start time. I changed the project start date time to be before Deb’s start time. Now tasks assigned to Deb are being scheduled correctly (Mon-Tues: 9.25 each AND Wed-Thurs: 9.5 each with Friday off).