Reply To: Actuals and Planned Hours Disappeared From Timecard

Home Forums Discussion Actuals and Planned Hours Disappeared From Timecard Reply To: Actuals and Planned Hours Disappeared From Timecard

#408753
John Murphy
Member

Daryl,

We are using Project Online and Project 2016.

The Actuals and Plan hours are disappearing from the Project Online Timesheet time-scaled cells where you enter daily hours. The task type is a Fixed Units. The task has a Finish No Earlier Than Constraint.

Thanks
John