Reply To: Team Member cannot see a project in the project center

Home Forums Discussion Team Member cannot see a project in the project center Reply To: Team Member cannot see a project in the project center

#409365

Two things I’d look at;
1) Is there a filter set in the Project Center view?
2) Is the resource assigned to the project and is the booking type = proposed?
I’m guessing