Reply To: Null in Baseline Cost on Summary Task

Home Forums Discussion Null in Baseline Cost on Summary Task Reply To: Null in Baseline Cost on Summary Task

#409401

Heather
Verify that the Summary task cost field has a value in it.
If not, it may be that your Summary Task is set as a Manual Scheduled task. When a summary task is not Auto Schedule, task information from the detailed tasks below it will NOT summarize up to the Summary task.